Friday, 25 January 2013
Well yet again the weather has really tried to throw the team off track this week, but the battle hardened guys have soldiered on and gone about their tasks with mininum fuss or distraction from the conditions. The Groundworker was back with us this week and he started by clearing the snow from the site then commenced with the works of installing the services to the flats. Meanwhile inside the flats the plastering was completed, the joiner was working his way through the flats doing the second fixing and the plumber had started his second fix to the upstairs flats.
Friday, 18 January 2013
The weather has certainly tried to dampen the spirits of the team this week, but to their credit they have battled on and got stuck into their tasks for the week. The plaster boarders have completed on site today leaving the plasterers to skim the last flat next week. The joiner has been back on site and he has started to second fix the first floor flats. The decorator came at the start of the week to mist coat the flats where the plaster had dried. We are now gearing up for the utility supplies to be installed in the next couple of weeks.
Friday, 11 January 2013
We were back up to a full compliment at the start of the week, with the whole team feeling refreshed and fully recharged after the Christmas break!
Joining the team on Monday were the plasterers, who made in-roads into the skimming of the flats, and by the end of the week three of the flats were completely plastered out.
The boarders carried on from where they left off, with the closing up of the walls and ceilings to the remaining flats and just about keeping in front of the plasterers.
The joiner was back with us finishing off the first fix to the flats also.