On Monday the bricklayers continued as much they could in the rain. Inside the flats the plaster boarders continued to board the walls and ceilings. Mid week we had the scaffold adapted so the bricklayers could continue to bring the front elevation up to the same level as the other elevations. Towards the end of the week the joiner started on site with fixing of the internal door frames.
Friday, 30 November 2012
Friday, 23 November 2012
This week the joiners joined the site team and started to fit the acoustic floors to the upstairs flats, whilst downstairs the plaster boarders were continuing their work in boarding the ceilings and walls the of flats. Externally the bricklayers progressed well with the brickwork finishing the week off at first floor level.
Friday, 16 November 2012
On Monday the plaster boarders joined us on site to start the boarding to the ceiling and the perimeter boards to the flats upstairs. The brickwork is continuing at a good pace externally and the entrance doors have been fitted. The plumbers were also on site to fix the guttering now the roof is complete.
Monday, 12 November 2012
At the start of the week the bricklayers started with us on site, they set their stall out at the rear elevation and got started on the brickwork. The roofers continued to make good progress with the tiling and were completed in time for the weekend. The window fitter came to site on Wednesday to commence with the window installation. Inside the building the insulation team began laying the insulation to the agreed areas.
Friday, 2 November 2012
At the start of the week, the timber framing team continued to battle the elements at the appropriately named 'Windy Bank' site ! They were working their way through all the finishes to the timber frame structure.
On Thursday the roofer started with us, and by the weekend the building will be water tight.
Next week the tiles will be delivered and we can then start tiling the roof.