Friday, 19 October 2012

Monday saw the start of the sole plates being fixed down for the arrival of the timber frame on Wednesday. We were all ready and raring to go on Wednesday when the crane and the first delivery of timber frame panels arrived. The guys worked hard to get all the ground floor panels unloaded and in place by the end of the day. Thursday we were erecting the smaller panels in readiness for the next crane and delivery of panels on Friday. Friday we had another hectic day with the floor cassettes arriving early morning and the roof trusses being delivered mid afternoon.
 


 