At the start of the week the bricklayers started with us on site, they set their stall out at the rear elevation and got started on the brickwork. The roofers continued to make good progress with the tiling and were completed in time for the weekend. The window fitter came to site on Wednesday to commence with the window installation. Inside the building the insulation team began laying the insulation to the agreed areas.