Friday, 1 March 2013

We are into the last month of works on site now and everything is moving nicely towards completion with the final decorations within the flats taking place. Once a flat is completed by the decorator the door is locked and should any other trade require entry to a finished flat they will be asked to sign the key out. Doing this reduces the risk of any potential damage to the finished flats therefore eliminating revisits by the decorator. This is especially important at this stage of the project as we enter the run in to handover. Testing and commissioning of the mechanical and electrical services has commenced. The joiner is working his way round hanging the pre-finished doors. Externally the flagging to the front elevation is complete. 
 


 