Friday, 17 August 2012

The foundations have now all been poured at Second Avenue, and we are well underway with the foul and surface drainage connection in the road.




Prior to this, we completed a cut and fill exercise to bring the ground up to formation level.


We have also drilled and grouted approximately 70nr boreholes to stabilise the ground, as history shows there was potentially old mine works in this area.


Next week we will be completing the outfall connections in the road, and commencing internal main drainage, including the storm water attenuation tank.