Monday, 24 September 2012

Over the past couple of weeks, the ground workers have been getting stuck in and laying all the drainage so they can put stone around the building, ready for the scaffold starting the middle of this week.  The concrete beam and block floors got put down last week, so now the guys are putting the gas membrane down and dropping the floor insulation on top.  We can then pour the concrete floor slab this week.

The bricklayers have been back on site, setting out the block up stand for the timber frame to sit on, and this also acts as a barrier for the concrete when it's poured. This sets us up nicely for the timber frame to start next week....