Firstly we would like to take this opportunity to sincerely thank all the local residents for their continued patience whilst we have been carrying out essential works in the road. This has enabled the team to install the electric supply to the flats. These works paired with the water connection have been a logistical nightmare, but with some good planning and precision they have been completed with minimum disruption. Internally the joiner has been continuing to fit the kitchens which are now 85% complete and the plumber has fitted 50% of the bathrooms leading to the tiler commencing on site to carry out the ceramic tiling to the walls in these areas. Next week we will progress externally with areas being prepped up for the flagging to commence in the not too distant future.