Friday, 15 February 2013

With all the kitchens now complete the joiner has continued with the second fix items such as boxing in the pipes to the bathrooms, the plumbers have now completed their works installing the basins. The tiler has completed all the tiling to the kitchens and bathrooms so in turn this brings the decorator back into play to carry out all the remaining decorations to the flats. To ensure the best possible finish we will have the power and the heating on to the flats in time for their arrival. Externally the team have been making in roads to the perimeter with the build up and compacting the stone for the flagged areas. Earlier in the week we installed the rain water harvesting tank and back filled so we could continue with the stoning up.
 
 
 
 